Construction Progress: 900 11th Street SE Condo

It was in Summer 2014 that plans were first made public on this project.  Construction did not get under way until Summer 2016.  The developer–Madison Investments–expects the building to be completed by Summer 2017.  Sigal Construction Corporation is the builder; Chuck Yetter, the project manager.

For more details and background information on this 49-unit condo project, go to Planned Condo Building for 11th & I Streets SE posting.  Most of the photos below are the view from the northeast corner of 11th and I Streets SE.

In mid-February 2017, the building was “topped out” and in September 2017 construction is in the final stages.  Sales of the 1 and 2 bedroom condos, priced from $450k to $900k, are underway. There is a roof deck and the 27 parking spaces underground are for sale, separately from the condo units.

September 22, 2017

900 11 9-22
View looking south along 11th Street SE

June 29, 2017

900 11 6-29
View looking NE from Gingko’s Across 11th Street SE

March 30, 2017

900 11 SE Mar 30 2017
Windows are in; facade brick going on

February 15, 2017

Ongoing Installation of Windows, 2/15/17

January 31, 2017

900 11SE Jan31-17 V1
Corner of 11th & I SE, 1/31/17

December 18, 2016 and earlier

Rear of building from I Street SE, 12/28/16
Rear of building from I Street SE, 12/28/16
900 11SE corner Dec 28
View from corner 11th & I, 12/28/16
900 11SE Nov 8 V2
Central core rises 11/8/16
900 11SE Nov 1
Rising Above 2nd Floor, 11/1/16
900 11SE  Oct 21
Second Floor Poured, 10/21/2016
900 11SE Oct11
Ground Floor Set, 10/11/16
900 11SE Sept26
Foundation & Supporting Columns, 9/26/16
900 11SE Aug 2016
Foundation Work August 22, 2016